2018
2018
In 2018 workers of JSC “Tatavtodor” had successfully finished construction, reconstruction and repair of 143 sites on public auto roads, total cost of works is 5.5 billion rubles. Total length of roads reconstructed for the reporting period is 271 km, in which 58.2 km of municipal auto roads were reconstructed as part of the following programs:
Works for implementation of municipal program for conduction of road works on the public local auto roads for year 2018 in the Republic of Tatarstan.
Total cost of works – 108 million rubles, total road length 9.1 km, works conducted in 5 municipal districts of the Republic of Tatarstan;
Reconstruction of asphalted road network in the district centers and cities of the Republic of Tatarstan.
Total cost of works – 347.7 million rubles, total road length 24.9 km, works conducted in 13 municipal districts of the republic.
Normalization of road network in the inhabited localities of the Republic of Tatarstan (transitional type of road surface).
Total cost of works – 227.8 million rubles, total road length 24.2 km, works conducted in 11municipal districts of the republic.
For the reporting period, access roads with solid surfacing were constructed in 16 inhabited localities with total population of more than 2000 people. Works were conducted at 14 sites with total length of 63.5 km in 12 municipal districts of the republic including 8 sites with transitional type of surface with total length of 27.5 km. In 2018 our company was an active participant of the federal program “Sustainable development of rural territories for 2014-2018 and for the period until 2020” (see list of works fulfilled as a part of the program below):
District
|
Site
|
Locality
|
Length, km
|
Asphalted surface type
|
Aktanyshsky
|
Reconstruction of the access road to Nizhneye Yakhsheyevo village
in Aktanyshsky municipal district of the Republic of Tatarstan
|
Nizhneye Yakhsheyevo village
|
1.116
|
Kukmorsky
|
Reconstruction of the auto road Yatmas-Dusai-Shepshenar in Kukmorsky municipal district of the Republic of Tatarstan
|
Shepshenar village
|
2.870
|
Menzelinsky
|
Reconstruction of the auto road М-7 “Volga”- Novyi Melken in Menzelinsky district of the Republic of Tatarstan
|
Novyi Melken settlement
|
9.913
|
Musliumovsky
|
Reconstruction of the auto road М-7 “Volga”- Staroye Aymanovo-Oktyabr, part Tatarskoye Bulyarovo-Urazmetyevo in Musliumovsky municipal district of the Republic of Tatarstan
|
Tatarskoye Bulyarovo village,
Urazmetyevo settlement
|
6.120
|
Reconstruction of the auto road Musliumovo-Staroye Saitovo, part Semyakovo-Staroye Saitovo in Musliumovsky municipal district of the Republic of Tatarstan
|
Staroye Saitovo village
|
13.213
|
Sarmanovsky
|
Construction of the auto road “Dzhalil-Sarmanovo” - Kulmetyevo in Sarmanovsky municipal district of the Republic of Tatarstan
|
Kulmetyevo village
|
2.732
|
Transitional surface type
|
Aksubayevsky
|
Reconstruction of the road network in the inhabited localities of Aksubayevsky municipal district of the Republic of Tatarstan (transitional surface type)
|
Akhmatka village
|
3.606
|
Atninsky
|
Reconstruction of the auto road “Kshklovo- Kzyl-Utar in Atninsky municipal district of the Republic of Tatarstan
|
Kzyl-Utar illage
|
4.960
|
Buinsky
|
Construction of the auto road “Access road to Malye Shikhirdany villlage” in Buinsky municipal district of the Republic of Tatarstan
|
Malye Shikhirdany villlage
|
1.356
|
Vysokogorsky
|
Construction of the auto road Access to Bolshoy Pochinok village in Vysokogorsky municipal district of the Republic of Tatarstan
|
Bolshoy Pochinok village
|
2.026
|
Laishevsky
|
Reconstruction of the auto road Laishevo-Kurmanakovo, part km 7+881 – km 12+466 in Laishevsky municipal district of the Republic of Tatarstan
|
Kurmanakovo settlement
|
4.585
|
Mamadyshsky
|
Reconstruction of the auto road Uzyak-Alga-Petrovsky in Tiulyachinsky municipal district of the Republic of Tatarstan
|
Alga village – Petrovsky settlement
|
5.745
|
Menzelinsky
|
Construction of the auto road “M-7 “Volga” – Noviy Melken – Dusai-Kichu in Menzelinsky municipal district of the Republic of Tatarstan
|
Dusai-Kichu village
|
2.938
|
Tetiushsky
|
Construction of the auto road Access to Krasnye Tarkhany settlement in Tetiushsky municipal district of the Republic of Tatarstan
|
Krasnye Tarkhany settlement
|
2.281
|
In 2018 the company participated in the program for overall development of transportation infrastructure of Naberezhnye Chelny urban complex as a part of priority project, “Safe and quality roads”. The works were conducted on Avtozavodsky avenue from Chulman to Suyumbike avenues and on Vakhitova avenue from Chulman to Suyumbike avenues. Total length of the reconstruction site - 1.427 km, total cost – 98.2 million rubles.
|